Big things are happening on the Atlanta BeltLine! In addition to over seven miles of completed trail segments, there is active construction work on the BeltLine, and several segments are in various planning and design stages. Explore design and construction projects in progress.
Map View
List View
Project Name | Location | Description | Subarea |
---|---|---|---|
Northeast Trail (North)- Segment 3 and Connector Trails | Buford Highway to MARTA Lindbergh Station | This project will design, bid out, and build 2.4-miles of mainline trail from Buford Highway to... | 6, 7 |
Westside Trail – 1385 Ralph David Abernathy Access Point | Westside Trail near Ralph David Abernathy Blvd | The aim of this project is to provide an access point to the Westside Trail at Ralph David... | 1 |
Southside Trail – Segments 2, 3, 4, 5 | I-75 Underpass to Bill Kennedy Way | The project includes the design of a 14 foot wide concrete multi-use path and extending... | 2, 3 |
Northwest Corridor – BeltLine Trail Alignment Study | Northern terminus of the Westside Trail at Huff Road to the northern end of the Northeast Trail at Armour-Ottley | The Northwest Trail is a critical quadrant of the Atlanta BeltLine loop connecting from the area... | 6, 7, 8, 9, 10 |
Eastside – Ponce Streetscape Project | Ponce De Leon Avenue from Boulevard to Freedom Parkway | The streetscaping of Ponce De Leon Avenue (State Road 8) extends from Boulevard/Monroe Drive to... | 6 |
Northeast Trail – Segment 1 (Piedmont Park) | Piedmont Park (Monroe Drive to Westminster Drive) | The Northeast Trail - Segment 1 runs 0.9 miles from Monroe Drive to Westminster Drive with a... | 6 |
Westside – Enota Park | Enota Park located adjacent to the Westside Trail in the Westview neighborhood | Enota Park is a +/- 8-acre park comprised of three parcels – identified as the Upper, Middle,... | 1 |
Southside – Boulevard Crossing Park | +/- 25-acre park located at the intersection of Boulevard and Englewood SE | This is Phase II of the design of Boulevard Crossing Park. The first phase of the park, which... | 3 |
Westside Trail – Segment 3 (Marietta Blvd) | Westside Trail Segment 3 is mainline BeltLine trail | Westside Trail - Segment 3 is mainline BeltLine trail and runs 1.22 miles from Law Street to... | 10 |
Southside Trail – Segment 1 (West Segment) | Terminus of Westside Trail at Allene Ave to Pittsburgh Yards | Southside Trail - Segment 1 is the first of five segments of the Southside Trail to be completed... | 2 |
Southside Trail – Utility Coordination | Terminus of SST-W to Glenwood | For the Southside Trail Segments 2, 3, 4, and 5, ABI will begin the process of coordinating any... | 2, 3 |
Northeast Trail – Segment 2 | Westminster Drive to Mayson Street | Northeast Trail - Segment 2 opened in November 2023 and is 1.2 miles in length between... | 6 |
Westside Trail – Segment 4 | Lena Street (existing Westside Trail terminus) to Law Street (tying into the Westside BeltLine Connector); Subareas 9 and 10 | The northern extension of the Westside Trail, also called Westside Trail - Segment 4, begins at... | 9, 10 |
Westside – Ralph David Abernathy – Streetscape | Ralph David Abernathy Blvd | The Ralph David Abernathy Blvd Streetscape project runs between Willard Avenue and East Ontario... | 10 |
Northwest Trail – Segments 1, 2, 3, 4, 5 | Northern terminus of the Westside Trail at Huff Road to the northern end of the Northeast Trail at Armour-Ottley | The Northwest Trail will run 4.3 miles from the northern terminus of the Westside Trail (in the... | 6, 7, 8, 9, 10 |