Design

Southside Trail – Segments 2, 3, 4, 5

I-75 Underpass to Bill Kennedy Way // Subarea 2, 3

The project includes the design of a 14 foot wide concrete multi-use path and extending approximately 3.1 miles from the paved trail at Pittsburgh Yards (near the I-75 underpass) to the end of the unpaved Southside Trail at Bill Kennedy Way. Southside Trail – Segments 2 and 3 make up 1.9 miles and Segments 4 and 5 are 1.2 miles.

Additional site elements include planting, lighting, retaining walls, vertical connections to adjoining streets, storm drainage, signage/wayfinding, and the replacement and rehabilitation of several bridges. The design also includes streetscape/accessibility improvements on all intersecting streets extending from the corridor to the nearest intersection or one-quarter mile, whichever was closest.

ABI was awarded a $500,000 Brownfield Cleanup Grant from the Environmental Protection Agency (EPA). Grant funds will be used to clean up portions of the interim Southside Trail. Soil remediation will focus on 26 areas as identified in the Analysis of Brownfield Cleanup Alternatives (ABCA) previously prepared by United Consulting. The Analysis of Brownfield Cleanup Alternatives (ABCA) is available for viewing here. The report, part of an EPA grant, provides information about any contamination found on site and alternatives for cleaning up any the contamination.

Southside Trail design and construction status June 2023
Southside Trail design and construction status as of June 2023.

Project Status

The Southside Trail has project has been broken into six segments.

  • Southside Trail – Segments 2 – 3: The construction of Segments 2 and 3 has been released to bid.  Construction bids are currently expected in February. The goal is to begin trail construction in late spring of 2024, with a two year construction schedule.  This project achieved the highest level of federal funding possible at 80% of the total construction budget.
  • McDonough Tunnel: ABI has hired an engineering consultant to design potential solutions where the interim trail is flooding in the McDonough tunnel. Design engineering is complete, and pricing is in progress with a contractor. ABI will proceed with recommendations which includes the installation of drainage piping and additional gravel, while balancing cost, since this section of trail will be under construction very soon.
  • Southside Trail – Segments 4 – 5: Current activities include the installation of storm piping and structures underground that will mitigate and manage storm water on the completed project. The contractor is working currently at Delmar and heading south towards Ormewood Ave. Sidewalks and some on-street parking on Ormewood Ave. was closed off to allow for the installation of a new pedestrian bridge. Pile driving is in progress for the bridge structure, or bridge bents at Ormwood Ave. and columns to support the new bridge are being poured. Construction of a retaining wall is in progress for a future access ramp to Delmar Ave., SE.  The trail will remain closed for the duration of construction, expected to last through spring 2025. Detour options can be found here.
  • Manford Road Streetscapes: This project will get underway in once the contractor has received all permits, and will include the construction of connecting sidewalks to the Southside Trail from the Capitol View Manor neighborhood. All permits have been requested and are expected to be received in early 2024. Construction hours will be from 7 a.m. to 5 p.m. between Monday and Friday and the project is expected to last no longer than six weeks.
Atlanta BeltLine Southside Trail detour option between Glenwood Avenue and Boulevard.
Atlanta BeltLine Southside Trail detour option between Glenwood Avenue and Boulevard.
Atlanta BeltLine Southside Trail detour option from United Avenue access point.
Atlanta BeltLine Southside Trail detour option from United Avenue access point.
Atlanta BeltLine Southside Trail detour option from the west side of the Mercer Street access point.
Atlanta BeltLine Southside Trail detour option from the west side of the Mercer Street access point.
Atlanta BeltLine Southside Trail detour option from the east side of the Mercer Street access point.
Atlanta BeltLine Southside Trail detour option from the east side of the Mercer Street access point.

Project Timeline

March 2018
The City of Atlanta and ABI purchased the southside corridor, representing more than 4 miles and 63 acres
August 2019
The Southside Trail opened for public use in an unpaved condition
July 2020
Emergency demolition of bridge over United Avenue
May 2021
Interim safety improvements along Bill Kennedy Way (Southside Trail - Segment 6) completed
May 2021
ABI awarded $4 million in grant funding from the Atlanta Regional Commission
November 2021
RAISE grant awarded for $16.46 million towards construction
August 2022
Brownfield remediation work completed by Reeves Young
August 2022
Invitation to Bid posted for construction of Segments 4 and 5
2022-early 2023
Utility relocation and remediation work
May 2023
Construction began on Segments 4 and 5
November 2023
Segment 2 and 3 will be released for big for construction
Spring 2024
Goal to begin trail construction on Segments 2 and 3

Last Updated: December 26, 2023